To ensure the network is performing at its peak, our Network team are undertaking a program of maintenance works in May 2025.

The majority of the works will take place in the morning during the at-risk period (or earlier): 7.30-8.30am, with the exception of the first stage of the upgrade work which is planned for a weekend.

The following are the planned dates for work to take place:

  • Weekend of 17/18 May (no outages expected)
  • Thursday 22nd May (no outages expected)
  • Tuesday 27th May (all Wi-Fi services will be impacted)
  • Tuesday 3rd June (all Wi-Fi services except UoS Guest Wi-Fi will be impacted, VPN also impacted)

We have attempted to plan these works around the core teaching/exam timetables but please contact us as soon as possible via the Information Centre if you anticipate these dates causing any problems.